“How long does planning permission take in Ireland?” is usually asked when a project already has a target start date. The statutory decision period is eight weeks, but the full timeline from first idea to a final grant is longer, and it depends heavily on how well the application is prepared. This guide sets out each stage, the statutory periods, and what changes for applications made under the Planning and Development Act 2024 from 26 November 2026.
Last checked: 19 November 2026. This is general information, not legal advice. Statutory periods can be affected by holidays, further information requests and the transition to the 2024 Act.
Stage 1: Preparation
Before an application is lodged, the proposal needs to be designed and checked against the county or city development plan, the planning history of the site and any constraints, such as flood risk, protected structures, conservation areas, road access or wastewater treatment. Depending on the project, supporting reports may be needed, for example a site suitability assessment for a rural house or a heritage impact assessment.
The time this takes varies widely. A straightforward extension may be ready within a few weeks; a one-off rural house or a commercial change of use can take considerably longer. Many councils also offer pre-planning consultation, which needs to be booked in advance.
Stage 2: Public notices and lodging the application
The applicant must publish a notice in an approved local newspaper and erect a site notice. The application must be received by the council within two weeks of the newspaper notice, and the site notice must be in place on or before the day of lodgement and remain in place for the required period, which Citizens Information gives as at least five weeks. The days from 24 December to 1 January are not counted when calculating that period.
From 26 November 2026, new applications must use the forms and notices prescribed under the 2024 Act. Notices or forms that still refer to the Planning and Development Act 2000 risk the application being declared invalid. See our update on the Planning and Development Act 2024.
Stage 3: Validation
The council checks that the application is complete and compliant. An invalid application is returned and must be re-advertised and re-lodged, which can add several weeks. Validation problems are among the most avoidable causes of delay.
Stage 4: Public submissions
Members of the public can make submissions or observations within five weeks of the council receiving the application. Under the draft regulations for the 2024 Act, the period remains five weeks, and the council cannot decide the application until six weeks after it is received.
Stage 5: The decision
The council must generally decide a valid application within eight weeks of receiving it. The decision will be a notification of a decision to grant, with conditions, or a decision to refuse, with reasons.
Further information
Instead of deciding, the council may request further information. Under the 2000 Act, the decision is then generally due within four weeks of the response, and significant further information can require fresh public notices and a new submission period. Under the 2024 Act, a further information request may be made only once and is limited to specific matters. Either way, a further information request typically adds weeks or months, which is why a complete application matters.
Stage 6: The final grant
If the council decides to grant permission and no appeal is made within the four-week appeal period, the final grant of permission issues shortly afterwards. Work should not start until the final grant has issued and any pre-commencement conditions have been complied with. Building Control requirements, including a Commencement Notice where required, also apply.
Where an appeal is lodged with An Coimisiún Pleanála, the timeline is extended. The 2024 Act introduces statutory decision periods for the Commission for the first time. For most homeowners, though, the better route is to avoid an appeal through a well-prepared application.
A realistic overall timeline
For a straightforward application that is valid on lodgement and decided without further information, the minimum from lodgement to final grant is typically around three months: eight weeks for the decision plus four weeks for the appeal period and the issue of the grant. Add the preparation period before lodgement, and allow more time for further information, complex sites or the Christmas period.
How to avoid delays
- Check the planning history of the site and any existing permissions and conditions.
- Use the correct forms and notices, particularly around the 26 November 2026 changeover.
- Address development plan policies directly in the drawings and a short planning statement.
- Anticipate the obvious questions, such as overlooking, sightlines or wastewater, rather than waiting for a further information request.
Frequently asked questions
How long does a council have to decide a planning application?
Generally eight weeks from receipt of a valid application, longer where further information is requested.
When can I start building after a decision to grant?
After the final grant issues, which follows the four-week appeal period if no appeal is made, and after any pre-commencement conditions are complied with.
Does the 2024 Act make planning faster?
The 2024 Act introduces statutory timelines across the system, including for An Coimisiún Pleanála, and limits further information requests. How this works in practice will become clearer after 26 November 2026.
Talk to our planning team
Our planning team, led by a chartered planning consultant and Full Corporate Member of the Irish Planning Institute (MIPI), prepares complete, well-supported applications to reduce the risk of invalidation and further information requests. Our planning permission Ireland page explains our service, and our planning permission by county page links to every council.
Send us your project details →